“While you are here, could you also do this?” A small addition can change materials, time, access, and the final bill. The dangerous shortcut is editing the old estimate and assuming its approved label now covers the extra work.
The operating rule: preserve the accepted version, describe the difference, agree on the price and timing effect, and record the decision before carrying out the affected extra work. A new total in your software is not, by itself, evidence that the customer accepted that change.
This is a practical records workflow, not a legal contract template. Requirements depend on your location and work. For example, California CSLB guidance for home improvement contracts calls for a written change order signed by the customer and contractor before changing contract price or scope. Do not assume a casual text reply satisfies the rules for your job.
First decide what actually changed
| Situation | Record | Next action |
|---|---|---|
| A clarification within the agreed work. | The answer and the original scope reference. | Check that price, materials, and timing really remain unchanged. |
| An extra item or a requested substitution. | What is added or replaced, the difference in price, and timing dependencies. | Issue a separate change record or a clearly identified replacement version for acceptance. |
| The customer removes work. | What is removed and the agreed credit, if any, including relevant commitments already made. | Agree on the revised position; do not lose the credit when invoicing. |
| An unexpected site condition. | Observed facts, photos where appropriate, and affected work. | Pause the affected task and review the options. A discovered problem is not automatic authorization to charge for its repair. |
Ask one practical question: “Could a person who only saw the accepted estimate know we were going to do this?” If not, stop treating the change as an invisible note. Safety or emergency conditions need their own appropriate response; this workflow is not permission to continue unsafe work.
Why an Approved label is not enough
Jobber documents an important distinction. Certain edits to an approved quote, including line items or totals, remove the visible signature while a signed PDF of the earlier version is retained in an internal note. The quote can nevertheless remain Approved. To collect a fresh signature, its guidance describes returning the quote to Awaiting Response and resending it. That is documented product behavior, not a bug we discovered or a new test result. Jobber quote approvals.
Housecall Pro distinguishes the actor. Its documentation separates customer approval from a manual office action, which produces Pro Approved or Pro Declined. An internal status change and a customer-signed agreement are different evidence. Open the agreement or decision history instead of relying on the label alone. Housecall Pro approvals and signatures.
For any software, check the same four things: who made the decision, which version they saw, when they decided, and where the record is preserved. Do not manually mark a new version accepted merely to make the dashboard look tidy.
How to Get a Quote Approval | Quoting and Estimates
YouTube connects only after you choose to load this video.
The one-page change record
You do not need a complicated approval system to make the difference visible. Start with a record linked to the correct customer and job, then use the acceptance method required for your work.
- Original reference: estimate number, accepted version, date, and the unchanged base scope.
- Change reference: a unique number, version, issue date, and who requested it.
- Scope difference: additions, removals, substitutions, exclusions, and unresolved assumptions.
- Money difference: additions and credits separately, the revised subtotal, and how applicable taxes or fees will be handled.
- Timing difference: extra duration and dependencies such as materials, access, permits, or a separate visit. Do not invent a confirmed slot.
- Decision evidence: authorized decision-maker, acceptance method, timestamp, and a retained copy of the exact version.
- Operational handoff: who updates the work instructions, checks materials, and reconciles the invoice.
Preserve the original estimate even when your system creates a replacement version. If the price changes twice, keep the earlier proposal as superseded rather than deleting the trail. Stop old reminders and links from presenting that earlier proposal as current.
A message you can adapt before requesting acceptance
Hi [name], you asked us to change [specific item] on job [reference]. The attached change [number and version] shows what is added or removed compared with estimate [original reference and version].
The proposed adjustment is [addition] less [credit], with a revised [subtotal/total and tax treatment] of [amount]. The effect on timing is [verified impact or dependency]. The remaining agreed scope is unchanged.
Please review that version and use [the appropriate acceptance method] if you want to proceed, or contact us with questions. We will not start the proposed extra work while its acceptance is unresolved. We will confirm any revised booking separately.
Replace every placeholder and attach or link the right document. This message introduces the change; it does not replace required contract wording, cancellation information, signatures, or other local obligations. Never translate silence, an opened email, or “please explain the price” into acceptance.
Handle all four outcomes, not just yes
- Accepted: retain the decision, update instructions, and reconfirm capacity before promising a date.
- Declined: do not perform the rejected extra. Confirm whether the original work remains feasible and agreed.
- Pending: keep the proposed extra out of accepted work and invoice calculations. Send a proportionate clarification through the agreed channel if needed.
- Superseded: identify the replacement and stop treating the old change request as open. Do not count both versions in the total.
If a customer disputes the scope or authority of an approval, pause the affected commercial step and resolve that issue before sending routine collection reminders. A workflow status cannot settle a disagreement.
Need a signature for the extra? Put it on the change sheet.
Suppose the optional 90 on CO03 is for removing an old cabinet. The customer accepted estimate Q104, but that estimate does not cover disposal. Give the change sheet its own version. Name the job, the cabinet to be removed, what disposal includes, the extra 90 in the same currency as Q104, and the timing you can actually offer. Identify who must approve it before the crew starts.
In SignWell, Sent and Viewed tell you that the request is in progress, not that the change was approved. Its document status guide distinguishes completion by all signers from a document manually marked as signed. Open the completed PDF and check the job reference, version, scope and required signers. A status label alone cannot tell the dispatcher which cabinet to remove.
No new software needed: If the job and local rules allow it, use a numbered paper change sheet. Obtain the required signatures, give the customer a copy and retain that same version with the job. The office runs the same checks before releasing the extra.
Reconcile additions, credits, and pending options
Fictional small repair job, in one chosen currency, before tax or fees. These numbers illustrate recordkeeping; they are not a price recommendation.
| Record | Decision | Effect on accepted subtotal |
|---|---|---|
| Original estimate Q104, version 1 | Accepted | 480 |
| CO01: additional repair | Accepted | +120 |
| CO02: remove agreed finishing item | Accepted credit | −40 |
| CO03: optional extra quoted at 90 | Pending | 0 - not accepted |
| Reconciled accepted subtotal | 480 + 120 − 40 | 560 |
The invoice should explain those accepted changes without adding the pending 90 or forgetting the 40 credit. Check completed versus billable work, payment terms, taxes, fees, deposits, previous invoices, and payments separately. An accepted subtotal is not automatically the amount currently due.
A separate what-if: If all required signers later approve the correct CO03 and nothing else changes, the accepted subtotal becomes 650. In the original example CO03 is still pending and the subtotal stays 560. Neither a signature nor the higher subtotal establishes that the cabinet was removed or that payment is due. These are fictional records, not a SignWell account test.
Field exercise · 3 minutes
Can I start this extra work?
The job is already approved. At the door, the customer adds: Could you take the old cabinet away, too?
You send a separate change sheet. Which record comes back?
- Accepted job subtotal
- 560 Q104 + approved changes
- Proposed extra
- +90 CO03 · cabinet removal
Viewed only · accepted subtotal 560
Hold the cabinet removal.
- Crew instruction
- Follow the accepted scope only. Leave the cabinet in place.
- Evidence to get
- Ask for a decision on the current CO03. Opening the document does not approve it.
- Before invoicing
- Keep the extra 90 out. Check completed work and payment terms separately.
Earlier version signed · accepted subtotal 560
Match the signature to the change.
- Crew instruction
- Do not remove the cabinet on the strength of the older signature.
- Evidence to get
- Keep the earlier copy. Compare its job, version and scope with the current CO03. Request approval of the correct version.
- Before invoicing
- The earlier signature does not add 90 to this job. Leave the extra out while it is unresolved.
Correct version signed · accepted subtotal 650
Update the work order, not the amount due.
- Crew instruction
- Add the agreed cabinet removal to the instructions. Confirm crew availability and access before promising a time.
- Evidence to keep
- Retain the completed CO03 with Q104. Check the job, version, cabinet and required signers before handoff.
- Before invoicing
- 560 + 90 = 650 accepted. Signing alone does not prove the cabinet was removed or that 650 is due. Check completion, terms and earlier payments.
Fictional practice case. Figures are in the same currency, before tax and fees. Use the approval method required for the actual job.
Take it to the job
Your change sheet
Print the example or take a blank copy to complete on paper. This worksheet does not collect signatures, schedule work or create an invoice.
Edit the example before printing
Use fictional job references, not customer names or contact details. Changes stay on this page and disappear when you reload it.
Fictional example. No decision selected; the proposed 90 is not accepted.
No sign-up. The blank version leaves your edits untouched. Confirm the requirements for your job and location before using any sheet as a change order.
Your five-minute end-of-job check
Open the accepted base estimate, each change decision, the worker’s completion record, and the draft invoice together. Can you trace every added or removed invoice item back to a decision? Can the customer see what changed? Are rejected, pending, and superseded items excluded from accepted extras? Resolve any mismatch before sending.
For work not yet quoted, start with our quote-request form comparison and pre-send estimate checklist. For an estimate still awaiting its first decision, use the estimate follow-up message templates. Those earlier stages should not be confused with a change to work the customer already accepted.
Need a software starting point? The solo operator hub connects the tools without assuming a one-person business needs a full dispatch platform.
Editorial record
Who reviewed this page and what happens next.
Commercial relationships cannot change the evidence state, fit statement, caveats, or conclusion.
- Research and review
- Andre Ribeiro
- Published
- Last material review
- Next scheduled review
- Evidence scope
- Post-acceptance scope changes, signed copies, and invoice reconciliation. Vendor behavior is documented, not newly tested; the example is fictional.